Last week of Inside The Capital Project Content Series (ITCPS). For anyone new, each Wednesday I've shared a different challenge from complex capital project work and the article I developed on it.
For the last week I wanted to get into earned value management, and why it works on some projects and falls apart on others.
What struck me is how strongly it depends on progress measurement. Percent complete is a judgment call, and two superintendents looking at similar activities can reasonably report 50% and 70%. Both are acting in good faith, but the earned value calculation still ends up shaky. Using installed or completed quantities, where the work can be quantified, takes some of that judgment out.
The other piece is rules of credit. One group awards value when materials arrive, another waits for installation, a third goes by engineering milestones. Each is defensible on its own, and together they make performance across the project hard to compare. Setting those rules before execution separates EVM that scales from EVM that becomes a reporting exercise. Full article linked below.
Question for the Community: How does your team measure progress for earned value, and how much debate does that measurement still create?